This article shows how to create a manufacturing order hierarchy.

What is an order hierarchy 

The link between two manufacturing orders creates a hierarchy. For example if there is a semiprocessed item which complete the final product, the first one is called "Child order" and the second one "Master order".

How to lable a Master order to an order 

Follow the steps below to lable a Master order to an order: 

  1. From the pull-drawers of Bravo click on “Manufacturing
  2. Select the option "Manufacturing order
  3. Double click on the chosen manufacturing order 
  4. Click on "Edit"
  5. Select the sheet "Hierarchy
  6. Click on "Add parent
  7. Complete the box "Add relatiopnship between orders"
  8. Click on "Save"
  9. Click on "Save

NOTE: If the inserted master order is wrong is possible to delete it. Select the wrong master order and click on "Remove parent".

How to lable a Child order to an order 

  1. From the pull-drawers of Bravo click on “Manufacturing
  2. Select the option "Manufacturing order
  3. Double click on the chosen manufacturing order 
  4. Click on "Edit"
  5. Select the sheet "Hierarchy
  6. Click on "Add child"
  7. Complete the box "Add relatiopnship between orders"
  8. Click on "Save
  9. Click on "Save"

NOTE: If the inserted child order is wrong is possible to delete it. Select the wrong child order and click on "Remove child". 